News Releases Archives - Florence Copper https://florencecopper.mystagingwebsite.com/category/news-releases/ In-situ Copper Recovery Thu, 08 Jan 2026 19:35:00 +0000 en-US hourly 1 https://florencecopper.com/wp-content/uploads/2023/09/cropped-FlorenceCopper_Site_Colour_Logo_PMS-32x32.png News Releases Archives - Florence Copper https://florencecopper.mystagingwebsite.com/category/news-releases/ 32 32 223216393 Taseko Provides Construction Update on Florence Copper Project | July 22, 2025 https://florencecopper.com/2025/07/23/taseko-provides-construction-update-on-florence-copper-project-3/ Wed, 23 Jul 2025 00:39:23 +0000 https://florencecopper.com/?p=1339       July 22, 2025, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to update the progress at its...

The post Taseko Provides Construction Update on Florence Copper Project | July 22, 2025 appeared first on Florence Copper.

]]>
 

 

 

July 22, 2025, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to update the progress at its 100%-owned Florence Copper project in Florence, Arizona.

At the end of June, construction of the commercial production facility was over 90% complete, and the project remains on schedule for first copper cathode production before the end of this year.  Over 900,000 project hours have been worked with no reportable injuries or environmental incidents on the project to date. Currently, there are approximately 330 construction and support personnel on site, down from the peak levels in the first quarter.

Stuart McDonald, President & CEO of Taseko, commented, “The first 18 months of construction has gone exceptionally well, demonstrating the quality and experience of our on-site owner’s team and contractors. Construction activities are advancing on plan and project areas will soon start the transition to commissioning.  A few notable milestones have recently been achieved.  In the wellfield, all the injection and recovery wells planned for the construction phase have now been drilled and completed. Drilling will recommence after plant commissioning to expand the current wellfield and allow for copper production to ramp up to the full 85 million pound per year plant capacity. Also, last week, a key component of the site infrastructure was completed with APS (the local utility) energizing the site 69kV electrical substation.”

“Operational readiness remains a key focus for site management.  Hiring full-time staff, training, and developing operational workflows are all ongoing to ensure our team is well-positioned for commercial operations in just a few months. A detailed operating plan for the 2026 ramp up is also being developed and will be finalized after acidification of the wellfield commences in the fall.”

“Florence Copper will be the next major U.S. supplier of domestically produced copper cathode. The potential for 50% tariffs on copper imports into the United States has driven the Comex copper price to record levels in recent weeks.  It’s a great time to be bringing on a new U.S.-based copper mine, and a high Comex copper price premium would provide a further boost to Florence Copper’s already strong project economics,” concluded Mr. McDonald.

For further information on Taseko, see the Company’s website at tasekomines.com or contact:

  • Investor enquiries Brian Bergot, Vice President, Investor Relations – 778-373-4554

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release

Caution Regarding Forward-Looking Information

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets and in the market price for our input costs including due to inflationary impacts, such as diesel fuel, acid, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar and our planned mining operations at Florence Copper, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to achieve reduced costs for Gibraltar (as defined below) and to otherwise control our operating costs without impacting our planned copper production;
  • our high level of indebtedness and its potential impact on our financial condition and the requirement to generate cash flow to service our indebtedness and refinance such indebtedness from time to time;
  • the increases in interest rates, by central banks may increase our borrowing costs and impact the profitability of our operations;
  • our ability to draw down on our financing arrangements for the construction of Florence Copper is subject to our meeting the required conditions for drawdown;
  • the amounts we are required to pay for our acquisition of Cariboo will increase with higher copper prices;
  • the risk of inadequate insurance or inability to obtain insurance to cover our business risks;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace Mineral Reserves as our existing Mineral Reserves are mined;
  • the risk that the results from our development of Florence Copper will not meet our estimates of remaining construction costs, operating expenses, revenue, rates of return and cash flows from operations which have been projected by the technical report for Florence;
  • the risk of cost overruns or delays in our construction of the commercial facilities at Florence Copper, resulting in not commencing commercial production within our current projected timeline or within our current projected cost estimates;
  • uncertainties related to the execution plan for the construction of Florence Copper and the commencement of commercial operations resulting from inflation risk, supply chain disruptions, material and labour shortages or other execution risks;
  • our ability to comply with all conditions imposed under the APP and UIC permits for the construction and operation of Florence Copper;
  • the availability of, and uncertainties relating to, any additional financing necessary for the continued operation and development of our projects, including with respect to our ability to obtain any additional construction financing, if needed, to complete the construction and commencement of commercial operations at Florence Copper;
  • shortages of water supply, critical spare parts, maintenance service and new equipment and machinery or our ability to manage surplus water on our mine sites may materially and adversely affect our operations and development projects;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition;
  • uncertainties related to Indigenous people’s claims and rights, and legislation and government policies regarding the same;
  • our reliance on the availability of infrastructure necessary for development and on operations, including on rail transportation and port terminals for shipping of our copper concentrate production from Gibraltar, and rail transportation and power for the feasibility of our other British Columbia development projects;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations;
  • potential changes to the mineral tenure system in British Columbia, which is undergoing reform for compliance with the Declaration Act (British Columbia);
  • our dependence solely on our 100% interest in Gibraltar for our revenues and our operating cash flows;
  • our ability to extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stockpiling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate mines, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mines;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to extreme cold, forest fires, flooding, drought, earthquakes or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to renegotiate our existing union agreement for Gibraltar when it expires in May 2027;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects including Florence Copper;
  • our ability to develop new mining projects may be adversely impacted by potential indigenous joint decision-making and consent agreements being implemented by the Government of British Columbia under the B.C. Declaration on the Rights of Indigenous Peoples Act;
  • our reliance upon key personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices and other input costs including diesel and acid;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates;
  • uncertainties relating to the war in Ukraine, the Israel-Hamas conflict and other future geopolitical events including social unrest, which could disrupt financial markets, supply chains, availability of materials and equipment and execution timelines for any project development;
  • recent changes to U.S. trade policies and tariff risks may adversely impact overall economic conditions, copper markets, supply chains, metal prices and input costs; and
  • other risks detailed from time-to-time in our annual information forms, annual reports, MD&A, quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedarplus.ca, including the “Risk Factors” included in our Annual Information Form.

 

 

 

The post Taseko Provides Construction Update on Florence Copper Project | July 22, 2025 appeared first on Florence Copper.

]]>
1339
Taseko Provides Construction Update on Florence Copper Project | April 25, 2025 https://florencecopper.com/2025/04/21/taseko-provides-construction-update-on-florence-copper-project-2/ Mon, 21 Apr 2025 15:31:11 +0000 https://florencecopper.com/?p=1239 April 21, 2025, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to update the progress at its 100%-owned Florence...

The post Taseko Provides Construction Update on Florence Copper Project | April 25, 2025 appeared first on Florence Copper.

]]>
April 21, 2025, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to update the progress at its 100%-owned Florence Copper project in Florence, Arizona.

Construction continues to advance on schedule and first copper production is still targeted before the end of 2025. Overall project completion was at 78% as of March 31, 2025. During the first quarter there were approximately 440 contract personnel on site and 230,000 project hours were worked. Total project hours to-date are roughly 670,000 and there have been no reportable injuries or environmental incidents.

Summary of key activities in the first quarter:

  • 29 production wells were drilled and constructed in the quarter, for a total of 80 out of the 90 wells planned to be drilled during the construction phase
  • Point of compliance well drilling was completed in the quarter
  • Work on the building structure for the electrowinning facility was completed except for the final roof and wall sections that will be installed after the electrowinning overhead crane is installed in April.
  • Installation of the cathode stripping machine started in March
  • The solvent extraction area continues to advance with a focus on pipe and settler welding and electrical installation
  • Hydrotesting of all the field erected tanks was completed
  • Sandblasting and painting of the carbon steel tanks was completed
  • Factory acceptance testing of the tank farm E-house was completed and it was delivered to site
  • Assembly of the modular office and dry buildings was completed, and work on the exterior finishing started
  • The substation area progressed and the installation of major equipment is well advanced
  • Work on surface infrastructure advanced and installation of high density polyethylene piping in the main pipeline corridor continued and the storm water box culvert under the pipe corridor was completed

Another significant recent milestone for Florence Copper is the authorization to reuse a portion of surplus process water from operations. Approximately 25% of the Florence Copper property is used for agriculture, and with the new permit, this excess process water will replace irrigation water that is currently drawn from other sources. This will result in more water available for other users in the project area.

Stuart McDonald, President & CEO of Taseko, commented, “After 15 months, construction progress continues to track to our original schedule. Wellfield drilling activity is now ramping down and will be completed on schedule in May, and we are steadily advancing towards first copper production later this year. Construction expenditures have been in line with expectations and our previous capital cost guidance remains unchanged. The project is in great shape and Florence Copper will soon become a major new supplier of copper cathode for the US market. The project is uniquely positioned to produce and sell refined copper inside the United States and potentially benefit from premium COMEX copper pricing in the coming years.”

Mr. McDonald continued, “Despite the recent market volatility, the long-term fundamentals for copper remain robust. In the short-term, Taseko has copper hedges in place that protect a minimum copper sales price of US$4.00 per pound for most of Gibraltar’s production for the balance of 2025.”

Updated photos can be found on our website at https://tasekomines.com/properties/florence-copper/#construction-updates.

For further information on Taseko, see the Company’s website at www.tasekomines.com or contact:

Investor enquiries Brian Bergot, Vice President, Investor Relations – 778-373-4554

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

Caution Regarding Forward-Looking Information

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.
Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel; and
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedarplus.ca, including the “Risk Factors” included in our Annual Information Form.

The post Taseko Provides Construction Update on Florence Copper Project | April 25, 2025 appeared first on Florence Copper.

]]>
1239
Taseko Provides Construction Update on Florence Copper Project | January 14, 2025 https://florencecopper.com/2025/01/14/taseko-provides-construction-update-on-florence-copper-project/ Tue, 14 Jan 2025 22:07:20 +0000 https://florencecopper.com/?p=1206 January 14, 2025, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to update the progress at its 100%-owned Florence...

The post Taseko Provides Construction Update on Florence Copper Project | January 14, 2025 appeared first on Florence Copper.

]]>
January 14, 2025, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to update the progress at its 100%-owned Florence Copper project in Florence, Arizona.

As of December 31, 2024, the overall project completion was at 56% and first copper production continues to be targeted before the end of 2025. Construction activities are advancing on schedule and nearly 450,000 project hours have been worked with no reportable injuries or environmental incidents. Currently, there are approximately 290 construction and support personnel on site.

Summary of key activities in the fourth quarter:

  • Process ponds and surface water runoff pond construction completed
  • Solvent extraction settler and launder modules placed and welding of the modules was commenced
  • 17 production wells were fully constructed in the quarter, for a total of 51 wells out of 90 to be drilled during the construction phase
  • Development of the main pipe corridor (from wellfield to process plant) is mostly completed and installation of high density polyethylene piping in the corridor is ongoing
  • Field erected process and service tank construction commenced
  • Mechanical and piping installations are underway throughout the SX/EW plant
  • Erection of structural steel for the solvent extraction pipe rack is nearing completion and piping installation is underway
  • Electrical work commenced
  • Water treatment building was erected, and preparations made to start the electrowinning building erection

Stuart McDonald, President & CEO of Taseko, commented, “We are very pleased with the progress that has been made in the first 12 months of construction. The project remains on schedule, and construction costs remain in line with our previous guidance. We are now less than a year from anticipated first copper production and, in addition to construction activities, our site management team is focused on operational readiness, key vendor agreements and recruiting.”

“With continued growth in US copper demand and an increasing focus on security of supply chains for critical materials, it is great timing to be bringing on a new source of domestic copper supply. Florence Copper is the only greenfield copper mine currently under construction in the USA and will soon become the third largest copper cathode producer in the country.”

“We have recently been informed that our application for the Department of Energy’s 48C(e) tax credit has been declined. However, Taseko remains in a strong financial position with C$330 million of available liquidity at year-end, including the undrawn US$110 million revolving credit facility,” concluded Mr. McDonald.

For further information on Taseko, see the Company’s website at www.tasekomines.com or contact: Investor enquiries Brian Bergot, Vice President, Investor Relations – 778-373-4554

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

Caution Regarding Forward-Looking Information

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel; and
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedarplus.ca, including the “Risk Factors” included in our Annual Information Form.

The post Taseko Provides Construction Update on Florence Copper Project | January 14, 2025 appeared first on Florence Copper.

]]>
1206
Taseko Mines Provides Construction Update for Florence Copper https://florencecopper.com/2024/10/22/taseko-mines-provides-construction-update-for-florence-copper/ Tue, 22 Oct 2024 19:43:34 +0000 https://florencecopper.com/?p=1190 October 21, 2024, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE MKT: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to provide a progress update for construction activities...

The post Taseko Mines Provides Construction Update for Florence Copper appeared first on Florence Copper.

]]>
October 21, 2024, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE MKT: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to provide a progress update for construction activities at its Florence Copper project.

To-date, approximately 300,000 project hours have been worked and there have been no reportable injuries or environmental incidents.  There are currently 280 construction personnel at site.  All activities are advancing on schedule and as of September 30, 2024, the project is approaching 40% complete.  First copper production is still anticipated in the fourth quarter 2025.

Since construction commenced earlier this year, the bulk of activities have been focused on earthworks, concrete, and wellfield drilling. Installation of structural steel, tanks, and process equipment is now underway.

Summary of key activities and status as of September 30, 2024:

  • Earthworks and site preparation for the plant area and commercial wellfield – ~75% complete
  • Concrete foundations for SX/EW plant and associated infrastructure – ~50% complete
  • Pre-assembly and installation of structural steel for the solvent extraction plant commenced in August
  • Installation of process equipment commenced in September
  • Powerline installation – ~65% complete
  • Wellfield drilling – a total of 34 production wells completed to date, out of a total of 90 to be drilled during the construction phase
  • Point of compliance well drilling – 9 wells completed to date, out of a total of 18
  • Construction of process and surface water runoff ponds
  • Hiring permanent operating staff – 75 of 170 total positions and all but one key management position has been filled

Stuart McDonald, President & CEO of Taseko, commented, “We are pleased with progress through the first nine months of construction.  With approximately 75% of total construction costs now committed, we expect total costs to be within 10-15% of the original US$232 million* estimate.  The project remains on track for first copper production in late 2025, which will be a transformative event for our Company.”

“In addition, we have applied to the U.S. Department of Energy’s Qualifying Advanced Energy Project Credit (48C) Program.  Florence Copper, which is set to become North America’s lowest GHG-intensity primary copper producer, qualifies as a critical materials project.  After submitting a concept paper in June, we received encouragement to proceed with the full application.  We have now filed the application seeking a tax credit of up to US $110 million, and we expect to hear whether Florence qualifies for the credit, or not, in January 2025” concluded Mr. McDonald.

The Company recently hosted a Florence Copper site tour and the associated presentation can be found at https://tasekomines.com/investors/documents-and-reports/corporate-presentations/. Additionally, updated construction photos can be found at  https://tasekomines.com/properties/florence-copper/#construction-updates.

*Based on the Florence Copper 43-101 Technical Report dated March 15, 2023, with costing basis Q3 2022.

 

For further information on Taseko, see the Company’s website at www.tasekomines.com or contact:

Investor enquiries Brian Bergot, Vice President, Investor Relations – 778-373-4554

Stuart McDonald

President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

 

Caution Regarding Forward-Looking Information

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • uncertainties about the continuing impact of the novel coronavirus (“COVID-19”) and the response of local, provincial, state, federal and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on our 87.5% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedarplus.ca, including the “Risk Factors” included in our Annual Information Form.

The post Taseko Mines Provides Construction Update for Florence Copper appeared first on Florence Copper.

]]>
1190
Taseko Provides Financing and Construction Update for the Florence Copper Project https://florencecopper.com/2024/01/16/taseko-provides-financing-and-construction-update-for-the-florence-copper-project/ Tue, 16 Jan 2024 09:00:27 +0000 https://florencecopper.com/?p=1055 January 16, 2024, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to provide an update on financing and construction progress...

The post Taseko Provides Financing and Construction Update for the Florence Copper Project appeared first on Florence Copper.

]]>
January 16, 2024, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to provide an update on financing and construction progress at its Florence Copper project.

On January 15, 2024, the Company signed a definitive agreement with Taurus Mining Royalty Fund L.P. (“Taurus”) for the previously announced sale of a US$50 million royalty.  The royalty will be for 1.95% of the gross revenue from the sale of all copper from Florence Copper.  Funding of the US$50 million is subject to customary closing conditions, and proceeds are expected to be received in early February.  The Company also expects to drawdown the first US$10 million of the US$50 million Mitsui financing later this month. With these financings in hand, construction activities at Florence will be accelerating.

To date, site activities have focussed on site preparations, earthworks and civil work for the commercial wellfield.  The initial drilling contracts are now being finalized, with drilling of the commercial facility wellfield to commence in February.  Additionally, the Company expects to sign a fixed-price contract with TIC Kiewit as general contractor for construction of the SX/EW plant and associated surface infrastructure.  All the major plant components are onsite and the build will begin in the second quarter of this year.

Stuart McDonald, President & CEO of Taseko, commented, “Signing of the Taurus royalty agreement is another positive milestone for the project. We are excited to be ramping up construction activities at Florence Copper, which will soon be a major new supplier of low-carbon copper cathode to the US market.

Site preparations and civil work are well advanced, and we’re looking forward to commencing wellfield drilling, with four rigs planned to be onsite initially. Construction of the SX/EW plant and other infrastructure represents a significant portion of the remaining project spend, and a fixed-price contract with TIC Kiewit will reduce inflationary risks, as Arizona continues to be a very active construction market.  Our early work on detailed engineering and procurement of long-lead items has significantly de-risked the construction schedule and we’re tracking towards first copper production in the fourth quarter of 2025.  We’re taking a disciplined approach to the buildout of the commercial facility at Florence, while our existing operations at the Gibraltar Mine continue to generate good cashflows in a strong copper price environment.”

“As an existing copper producer, Taseko is in an enviable and unique position with near-term, low cost production growth coming from a fully-permitted and environmentally beneficial copper project.  With copper now added to the US Department of Energy’s critical materials list, market interest in our project and future copper production remains strong,” added Mr. McDonald.

For further information on Taseko, see the Company’s website at www.tasekomines.com or contact:

Brian Bergot, Vice President, Investor Relations – 778-373-4533 or toll free 1-877-441-4533

Stuart McDonald

President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

 

Caution Regarding Forward-Looking Information

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our inpuh as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied agains has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • uncertainties about the continuing impact of the novel coronavirus (“COVID-19”) and the response of local, provincial and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our abilitieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting oupper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Coppethat provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineerinding updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below) and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for th our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due tarty opposition;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plantion risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities an and mine closure and bonding requirements;
  • our dependence solely on our 87.5% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate ourial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages oe to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Coppll>
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs sucel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated witting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedar.com, including the “Risk Factors” included in our Annual Information Form.

 

The post Taseko Provides Financing and Construction Update for the Florence Copper Project appeared first on Florence Copper.

]]>
1055
Taseko Mines Announces Receipt of Final Permit for the Florence Copper Project https://florencecopper.com/2023/09/14/taseko-mines-announces-receipt-of-final-permit-for-the-florence-copper-project/ Thu, 14 Sep 2023 20:16:54 +0000 https://florencecopper.com/?p=417 The post Taseko Mines Announces Receipt of Final Permit for the Florence Copper Project appeared first on Florence Copper.

]]>

September 14, 2023, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to announce that the US Environmental Protection Agency (“EPA”) has issued a final Underground Injection Control Permit (“UIC”) for the Florence Copper Project (“Florence Copper” or the “Project”).

Stuart McDonald, President and CEO of Taseko, commented, “Receipt of this final permit is an exciting milestone for Taseko and a testament to the project’s strong environmental attributes. We now have one of a very few construction-ready, fully permitted copper projects in North America. With approvals in place from the Arizona Department of Environmental Quality and now the EPA, we can commence construction of the Florence Copper commercial production facility. This achievement is a major stride forward and a result of Taseko’s long-term approach to project development, environmental protection, and community engagement.”

Mr. McDonald continued, “With procurement well advanced, the next steps will be mobilization of contractors for the wellfield and SX/EW plant construction. We continue to advance discussions with potential lenders and royalty providers for the remainder of the project financing package and expect to have additional commitments in place before construction spending ramps up.”

When commercial operations begin, Florence Copper will have an annual production capacity of 85 million pounds of copper at US$1.11 per pound C1 cash costs over a 22-year mine life. Based on a March 2023 Technical Report for the Project, which is supported by results from the successful operation of a production test facility, the Project has an after-tax NPV (8%) of US$930 million at a copper price of US$3.75 per pound.

“The Florence Copper Project is one of the least capital-intensive copper projects in the world and will have an environmental footprint smaller than any conventional open-pit or underground mining operation of comparable size. Low water use, low energy consumption and low carbon emissions make Florence Copper an exceptionally green project that will supply refined copper to the rapidly growing US domestic market,” concluded Mr. McDonald.

The Florence Copper NI 43-101 technical report is available on www.sedar.com or the Company’s website at www.tasekomines.com. For further information on Taseko, see the Company’s website at www.tasekomines.com or contact:

Brian Bergot, Vice President, Investor Relations – 778-373-4533 or toll free 1-877-441-4533

Stuart McDonald

President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

CAUTION REGARDING FORWARD-LOOKING INFORMATION

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • uncertainties about the continuing impact of the novel coronavirus (“COVID-19”) and the response of local, provincial, state, federal and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition, particularly in respect to Florence Copper that requires one key regulatory permit from the U.S. Environmental Protection Agency (“EPA”) in order to advance to commercial operations;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction once the final permit is received from the EPA;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on our 75% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedar.com, including the “Risk Factors” included in our Annual Information Form.

The post Taseko Mines Announces Receipt of Final Permit for the Florence Copper Project appeared first on Florence Copper.

]]>
417
Taseko Mines Receives Commitment For Additional Financing For Florence Copper https://florencecopper.com/2023/01/13/taseko-mines-receives-commitment-for-additional-financing-for-florence-copper/ Fri, 13 Jan 2023 21:11:14 +0000 https://florencecopper.com/?p=526 January 13, 2023, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to announce that it has obtained an underwritten...

The post Taseko Mines Receives Commitment For Additional Financing For Florence Copper appeared first on Florence Copper.

]]>
January 13, 2023, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to announce that it has obtained an underwritten commitment for US$25 million from Banc of America Leasing & Capital, LLC. Proceeds from this financing will be available to Taseko to fund costs associated with the Solvent Extraction and Electrowinning (“SX/EW”) plant for the Florence Copper commercial production facility.

“Following the recently announced strategic partnership with Mitsui & Co. (U.S.A.) Inc. for our Florence Copper project, this additional source of funds will further strengthen our balance sheet and provide financing flexibility as we prepare for construction of the project in 2023. We have a long-standing relationship with Bank of America, a North American leader in equipment financing for mines and projects directly supporting low-carbon initiatives in the United States,” stated Stuart McDonald, President and CEO of Taseko.

“In addition to Florence Copper’s strong economics, the project has many environmental attributes, including low carbon emissions and a low footprint operation, which are attractive to financial partners. The financing commitment from Bank of America is a customized solution developed for Taseko, leveraging the equipment security of our SX/EW plant, since conventional mining equipment like shovels and haul trucks will not be used at Florence Copper,” added Mr. McDonald.

Financing Details

The US$25 million of funding will be available for drawdown upon Florence Copper receiving the final Underground Injection Control permit from the EPA. The loan will be secured by specific treatment and processing equipment in the SX/EW plant with an initial term of five years. The facility can be repaid at any time and carries no financial covenants.

For further information on Taseko, please see the Company’s website at www.tasekomines.com or contact:

Brian Bergot, Vice President, Investor Relations – 778-373-4533 or toll free 1-877-441-4533

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

CAUTION REGARDING FORWARD-LOOKING INFORMATION

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • uncertainties about the continuing impact of the novel coronavirus (“COVID-19”) and the response of local, provincial, state, federal and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition, particularly in respect to Florence Copper that requires one key regulatory permit from the U.S. Environmental Protection Agency (“EPA”) in order to advance to commercial operations;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction once the final permit is received from the EPA;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on our 75% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedar.com, including the “Risk Factors” included in our Annual Information Form.

The post Taseko Mines Receives Commitment For Additional Financing For Florence Copper appeared first on Florence Copper.

]]>
526
Taseko and Mitsui Enter Strategic Partnership to Develop Florence Copper https://florencecopper.com/2022/12/20/taseko-and-mitsui-enter-strategic-partnership-to-develop-florence-copper/ Tue, 20 Dec 2022 21:11:45 +0000 https://florencecopper.com/?p=528 December 20, 2022, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to announce it has signed agreements with Mitsui...

The post Taseko and Mitsui Enter Strategic Partnership to Develop Florence Copper appeared first on Florence Copper.

]]>
December 20, 2022, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to announce it has signed agreements with Mitsui & Co. (U.S.A.) Inc. (“Mitsui”) to form a strategic partnership to develop the Company’s Florence Copper project (the “Project”), located in Arizona USA.

Mitsui has committed to an initial investment of US$50 million, with proceeds to be used for construction of the commercial production facility. The initial investment will be in the form of a copper stream agreement (the “Copper Stream”) on 2.67% of the copper produced at Florence Copper.

In addition, Mitsui has the option to invest an additional US$50 million (for a total investment of US$100 million) for a 10% equity interest in Florence Copper (the “Equity Option”). The Equity Option is exercisable by Mitsui within a three-year period following completion of construction of the commercial production facility.If Mitsui elects to exercise its Equity Option the Copper Stream will terminate.

As part of the arrangement, Taseko and Mitsui have entered into an offtake contract for 81% of the copper cathode produced at Florence during the initial years of production. The parties intend to use this period to develop premium sales channels for ‘green copper’ in the United States, leveraging Mitsui’s existing US cathode trading business and the unique environmental benefits of Florence Copper, which is expected to be the lowest carbon- and energy-intensity copper producer in North America.

Stuart McDonald, President & CEO of Taseko, stated, “This agreement with Mitsui establishes a strategic partnership with a leading international company. Mitsui’s investment will complement Taseko’s financing requirements and construction timeline and advance our goal of ensuring the copper produced at Florence is recognized for its unique low-carbon profile that will advantage US manufacturers and consumers. In the future, Taseko and Mitsui will collectively evaluate additional investments toward establishing Florence Copper as a zero-carbon copper producer (Scope 1 and 2).”

Sayu Ueno, President & CEO of Mitsui & Co. (U.S.A.), commented, “We are excited to partner with Taseko and its unique, low-carbon and low-impact Florence Copper project. When in production, Florence Copper will significantly expand our US cathode trading business, while providing an environmentally sound, domestically produced product that can be marketed on the basis of its low-carbon advantages. We believe Florence Copper will be a preferred source of ‘made-in-the-US’ copper for many end users in North America.”

 

Transaction Details

Under the terms of the initial US$50 million Copper Stream agreement, Mitsui’s first deposit payment of US$10 million will be available for drawdown after receipt of Florence Copper’s Underground Injection Control permit, with additional US$10 million instalments available each quarter thereafter to fund project construction. Mitsui will receive 2.67% of the copper metal produced at Florence and pay a delivery price equal to 25% of the market price of copper delivered under the contract.

If Mitsui elects to exercise its Equity Option and invest an additional US$50 million in the Project, these additional funds and the Copper Stream will be converted into a 10% equity interest in Florence Copper. At that time, the initial offtake agreement will cease and be replaced with a marketing agency agreement.

If the Copper Stream is not converted into an equity interest Taseko will have the right to buy-back 100% of the Copper Stream, otherwise, it will terminate when 40 million pounds of copper have been delivered under the agreement. Mitsui’s offtake entitlement would also reduce to 30% until the Copper Stream deposit has been reduced to nil.

About Mitsui & Co.

With a long history in the United States, Mitsui & Co. (U.S.A.), Inc. (“Mitsui USA”) is a wholly owned subsidiary of Mitsui & Co., Ltd., Tokyo, Japan, one of the most diversified and comprehensive trading, investment, and service enterprises in the world. Mitsui & Co. pursues “360° business innovation” that ranges from product sales, worldwide logistics and financing, through to the development of major international infrastructure and other projects. More information on Mitsui USA may be found at www.mitsui.com/us.

About Taseko

Taseko is focused on the operation and development of copper mines in North America. Headquartered in Vancouver, Canada, Taseko is the owner (75%) and operator of the Gibraltar Mine, the second largest open pit copper mine in Canada.Taseko’s Florence Copper Project in Arizona is a near-term growth project, which will nearly double the Company’s annual copper production. Construction of Florence Copper is expected to commence in 2023. Taseko’s Yellowhead Copper Project, New Prosperity Gold-Copper Project and Aley Niobium Project are all advanced staged projects which provide the Company with a diverse commodity pipeline.

For further information on Taseko, see the Company’s website at www.tasekomines.com or contact:

Brian Bergot, Vice President, Investor Relations – 778-373-4533 or toll free 1-877-441-4533

Stuart McDonald

President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

 

CAUTION REGARDING FORWARD-LOOKING INFORMATION

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • uncertainties about the continuing impact of the novel coronavirus (“COVID-19”) and the response of local, provincial, state, federal and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition, particularly in respect to Florence Copper that requires one key regulatory permit from the U.S. Environmental Protection Agency (“EPA”) in order to advance to commercial operations;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction once the final permit is received from the EPA;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on our 75% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedar.com, including the “Risk Factors” included in our Annual Information Form.

The post Taseko and Mitsui Enter Strategic Partnership to Develop Florence Copper appeared first on Florence Copper.

]]>
528
Florence Copper Permitting Update https://florencecopper.com/2022/10/04/florence-copper-permitting-update/ Tue, 04 Oct 2022 21:12:08 +0000 https://florencecopper.com/?p=530 October 4, 2022, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to provide an update on the federal permitting...

The post Florence Copper Permitting Update appeared first on Florence Copper.

]]>
October 4, 2022, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to provide an update on the federal permitting process for its Florence Copper project.

The U.S. Environmental Protection Agency (“EPA”) has now concluded the public comment period for the draft Underground Injection Control (“UIC”) permit that it issued in August 2022. Public comments submitted to the EPA have demonstrated strong support for the Florence Copper project among local residents, business organizations, community leaders and state-wide organizations. Over 98% of written comments were supportive of the project and supplement the unanimous public support voiced at the EPA’s public hearing on September 15, 2022. Taseko has reviewed all of the submitted comments and is confident they will be fully addressed by the EPA during their review, prior to issuing the final UIC permit.

“We have taken considerable time and worked extremely hard to demonstrate the environmental and societal benefits of our Florence Copper project. Florence Copper will have one of the lowest carbon footprints of any copper mine in the world and will produce a critical metal needed for the United States domestic market,” stated Stuart McDonald, President and CEO of Taseko.

For further information on Taseko, please see the Company’s website at www.tasekomines.com or contact:

Brian Bergot, Vice President, Investor Relations – 778-373-4533 or toll free 1-877-441-4533

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

CAUTION REGARDING FORWARD-LOOKING INFORMATION

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • uncertainties about the continuing impact of the novel coronavirus (“COVID-19”) and the response of local, provincial, state, federal and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition, particularly in respect to Florence Copper that requires one key regulatory permit from the U.S. Environmental Protection Agency (“EPA”) in order to advance to commercial operations;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction once the final permit is received from the EPA;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on our 75% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedar.com, including the “Risk Factors” included in our Annual Information Form.

The post Florence Copper Permitting Update appeared first on Florence Copper.

]]>
530
Update on Public Comment Period for Florence Copper UIC Permit https://florencecopper.com/2022/09/19/update-on-public-comment-period-for-florence-copper-uic-permit/ Mon, 19 Sep 2022 21:12:26 +0000 https://florencecopper.com/?p=532 September 19, 2022, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to provide an update on the federal permitting...

The post Update on Public Comment Period for Florence Copper UIC Permit appeared first on Florence Copper.

]]>
September 19, 2022, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) is pleased to provide an update on the federal permitting process for its Florence Copper Project. On September 15, the U.S. Environmental Protection Agency (“EPA”) held a virtual public hearing for the draft Underground Injection Control (“UIC”) permit issued for Florence Copper on August 15, 2022. Twenty-seven participants provided comment at the hearing, each supporting the project and calling for a final UIC permit to be issued. The UIC permit is the last authorization required to advance the Florence Copper Project to commercial production. The EPA public comment period is scheduled to conclude on September 29, 2022.

For further information on Taseko, please see the Company’s website at www.tasekomines.com or contact:

Brian Bergot, Vice President, Investor Relations – 778-373-4533 or toll free 1-877-441-4533

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

 

CAUTION REGARDING FORWARD-LOOKING INFORMATION

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • uncertainties about the continuing impact of the novel coronavirus (“COVID-19”) and the response of local, provincial, state, federal and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition, particularly in respect to Florence Copper that requires one key regulatory permit from the U.S. Environmental Protection Agency (“EPA”) in order to advance to commercial operations;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction once the final permit is received from the EPA;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on our 75% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedar.com, including the “Risk Factors” included in our Annual Information Form.

The post Update on Public Comment Period for Florence Copper UIC Permit appeared first on Florence Copper.

]]>
532